Physical Data Center Relocation - 13 Specific Tips for Smooth Migration

Physical Data Center Relocation - 13 Specific Tips for Smooth MigrationThe TDS data center relocation methodology follows a specific process to ensure smooth and successful data center relocation events.

We’ve outlined these 13 steps to give you some guidance on implementing a smooth data center migration.

1.  Thorough inspection and documentation of the source data center at least 2 weeks prior to scheduled move date

2.  All server related data entered into a purpose-built system (TDS’s unique TransitionManager™) which allows for simple generation of un-rack and re-rack plans and rack elevation diagrams to serve as working plans for the move engineers

3.  Bar Code Tagging of servers scheduled to move at least 2 weeks prior to the scheduled move date

4.  Data Center walkthrough (both source and target sites) 2 weeks prior to the move event with the lead move engineer and shipper to understand any special requirements or work to perform pre-move day

5.  Un-rack plan to maximize effectiveness and minimize overcrowding within the data center on move day

6.  System generated labels with server name placed on the rails when removed

7.  Rails are transported in advance if/where appropriate, to save time during the physical move process.

8.   System generated labels with server name, moving cart number, new row/rack location and U-Position are placed on the servers when removed

9.   Re-rack plan to maximize effectiveness and minimize overcrowding in the data center

10.  Rack elevation diagrams taped to each target rack for additional visual confirmation that servers are being racked in the proper locations

11.  Servers are unloaded and stacked on dollies designated for specific racks based upon detailed re-rack plan

12.  Connect all power and network cables based upon detailed re-rack plan

13.  Audit of rail installation, server locations and cabling is performed by a project manager or lead move engineer throughout the move and a final audit is performed upon completion

Learn more about this topic in our white paper Survival Guide for Data Center Migration


Back to resource library